Formula SSC-2026.1

4.00 / 12 · 18.43°

Pitch angle

18.43°

Multiplier 1.0541

Common rafter

15 ft 8 15/16 in

Tail 1 ft 5/8 in

Cuts

18.43° plumb

71.57° seat

Roof area

1,323 ft²

13.23 squares

Shingle bundles

44

3 bundles per square + 10% waste

Sheathing / felt

46 sheets

4 underlayment rolls

Delivery weight

5,308 lb

2,408 kg · 70 lb bundles, 46 lb sheets, 28 lb rolls

Gable truss triangleLive scaled blueprint
Span 28.00 ft + overhangsRise 4 ft 7 3/4 in124.04.0 : 12Rafter 15 ft 8 15/16 in · plumb 18.4° · seat 71.6°

Rise and run are scaled from the span, overhang, and pitch. The small triangle is the pitch ratio.

Bill of materials and shopping list
ItemNetWasteOrderUnit priceLine total
Architectural shingle bundles13.23 squares10%44 bundlesUSD$1,848.00
4x8 CDX sheathing41.3 sheets10%46 sheetsUSD$1,288.00
Underlayment rolls1,323 ft²overlap allowance4 rollsUSD$220.00
Ridge cap bundles42.0 ft ridge—2 bundles25 ft per bundle—
Side-by-side pitch comparison
PitchDegreesMultiplierRafterSquaresBundlesSheets
4.0/1218.43°1.05415 ft 8 15/16 in13.234446
6.0/1226.57°1.11816 ft 8 7/16 in14.034749
8.0/1233.69°1.20217 ft 11 7/16 in15.085052
12.0/1245.00°1.41421 ft 1 1/2 in17.745961
Show the deterministic formula

Angle = arctan(rise ÷ 12). Multiplier = √(1 + (rise ÷ 12)²). Gable run = span ÷ 2 − ridge thickness ÷ 2. Rafter length = (run + horizontal overhang) × multiplier.

Plumb cut = pitch angle. Seat cut = 90° − pitch angle. Area uses both slopes on a gable and one slope on a shed, and it includes a rake overhang equal to the eave overhang.

Bundles = ceiling of squares × 3 × 1.10. Sheets = ceiling of area × 1.10 ÷ 32. Rolls use 360 ft² effective coverage. Delivery weight plans 70 lb per bundle, 46 lb per sheet, and 28 lb per roll, then the header converts that pound total at 1 lb = 0.45359237 kg.

Engineering notes

A steeper pitch lengthens the rafter and grows the roof area even though the building footprint stays 28 by 40 ft. The working pitch is 4/12. The table repeats 4/12 and 8/12, and also shows 6/12 and 12/12 so the jump is not a single step. Overhang is 1 ft and the ridge is 1.5 in. Order the steeper roof only after you also check tie-downs and the rafter size, which this quantity tool does not do.

Code reference

IRC R802 and R905. Pitch changes area and length only in this calculator. Structural capacity is a separate check.

Field questions

Why does 8/12 need more shingles than 4/12?
The slope length is the horizontal run times a larger multiplier. Both slopes of the gable get longer, so the squares go up.
Is the building length included twice?
No. Each slope is rafter length times the building length plus rake overhangs. A gable has two slopes.
What overhang is in the area?