6×6 Hot Tub Pad, 6 Inch Reinforced

A small 6 ft square, 6 in pad with a tight rebar grid for a hot tub.

Formula SSC-2026.1

Formula SSC-2026.1 · 4,000 PSI

Order volume

0.70 yd³

0.535 m³ placed+waste

Order weight

2,835 lb

1,286 kg

80 lb bags

32

1 pallets at 42 bags

60 lb bags

42

0.45 ft³ yield each

Rebar

84.00 ft

14 × 20 ft · 14 × 6 m · 59 lb

Ready-mix vs bags

$216.00

Truck $240.50 · 80 lb bags $216.00

Slab footprint and rebar gridLive scaled blueprint
6.00 ft6.00 ft#4 / 12 mm at 12 in OC · 6 in slab

Grid lines are equalized so the drawing stays readable. The order count uses on-center spacing with a bar at each end of the layout, then holds concrete cover in the field.

Bill of materials and shopping list
ItemNetWasteOrderUnit priceLine total
Ready-mix concrete0.67 yd³5%0.70 yd³ / 0.535 m³USD$115.50
Short-load feeUnder 4 yd³—1 truck @ 10 yd³USD$125.00
80 lb pre-mix bags30.0 bags5%32 bagsUSD$216.00
60 lb pre-mix bags40.0 bags5%42 bagsUSD$226.80
#4 rebar sticks, 20 ft14 sticks5%15 sticks / 14 × 6 mUSD$210.00
Rebar chairs49 crossings5%52 chairsUSD$14.56
Tie wire rolls49 ties5%1 rollsUSD$8.00

Ready-mix truck

$240.50

0.07 nominal 10 yd³ loads · 1 to order

80 lb bags

$216.00

60 lb alternative $226.80 · delivery weight 2,835 lb

Side-by-side thickness comparison at the same footprint
ThicknessOrder yd³Order m³80 lb bagsRebar ftReady-mix80 lb cost
4 in0.470.3572188$202.00$141.75
6 in0.700.5353288$240.50$216.00
8 in0.930.7144288$279.00$283.50
Show the deterministic formula

Slab ft³ = L × W × thickness ÷ 12. Thickened-edge extra = footing band × (footing depth − slab thickness), with corner squares counted once.

yd³ = ft³ ÷ 27. m³ = ft³ × 0.0283168. Weight uses 150 lb/ft³, then the header converts that pound total at 1 lb = 0.45359237 kg. 80 lb bags yield 0.6 ft³ and 60 lb bags yield 0.45 ft³. Currency changes the price labels only.

Bars across a span = floor(span ÷ spacing) + 1. Order sticks = that count, plus 10, 5, or 15 percent waste, cut from 20 ft and 6 m stock. Chairs = one per grid intersection.

Engineering notes

A 6 by 6 ft pad at 6 in is 0.67 cubic yards before waste. That is a bag job unless you are already pouring something else. The default is #4 at 12 in on center and 5 percent waste. The order weight is the concrete only. Add the tub, water, and people on top of that number when you talk to the inspector. A filled tub is a concentrated load, so this page does not claim the pad is adequate by itself.

Code reference

IRC R506.1 sets a 3.5 in minimum for concrete slab-on-ground floors. Reinforcement cover and spacing follow ACI 318 practice and the local inspector. This quantity takeoff is not a soils or structural design.

Field questions

How much concrete is a 6x6 by 6 inch pad?
Placed volume is 18 cubic feet, or 0.67 cubic yards. With 5 percent waste the order is about 0.70 cubic yards.
Why is the grid at 12 inches?
The smaller spacing is a tighter mat for a point-loaded pad. It raises bar count, chairs, and tie intersections compared with an 18 in garage grid.
Does the weight include the water?
No. The weight is normal-weight concrete at 150 lb per cubic foot. The tub manufacturer publishes the filled weight you still have to support.