10 by 20 ft slab at 8 inches
Calculate the requirements for a residential slab measuring 10 ft by 20 ft at 8 in thickness with #4 bars at 18 in spacing. Note: Soil design is excluded.
Formula SSC-2026.1
Formula SSC-2026.1 · 4,000 PSI
Order volume
6.19 yd³
4.735 m³ placed+waste
Order weight
25,080 lb
11,376 kg
80 lb bags
279
7 pallets at 42 bags
60 lb bags
372
0.45 ft³ yield each
Rebar
400.00 ft
27 × 20 ft · 36 × 6 m · 294 lb
Ready-mix vs bags
$1,021.78
Truck $1,021.78 · 80 lb bags $1,883.25
Grid lines are equalized so the drawing stays readable. The order count uses on-center spacing with a bar at each end of the layout, then holds concrete cover in the field.
| Item | Net | Waste | Order | Unit price | Line total | Source Spec Material / Tool |
|---|---|---|---|---|---|---|
| Ready-mix concrete | 5.63 yd³ | 10% | 6.19 yd³ / 4.735 m³ | USD | $1,021.78 | Source Spec Material / Tool |
| Short-load fee | Full load | — | 1 truck @ 10 yd³ | USD | $0.00 | Source Spec Material / Tool |
| 80 lb pre-mix bags | 253.3 bags | 10% | 279 bags | USD | $1,883.25 | Source Spec Material / Tool |
| 60 lb pre-mix bags | 337.8 bags | 10% | 372 bags | USD | $2,008.80 | Source Spec Material / Tool |
| #4 rebar sticks, 20 ft | 27 sticks | 10% | 30 sticks / 36 × 6 m | USD | $420.00 | Source Spec Material / Tool |
| Rebar chairs | 98 crossings | 10% | 108 chairs | USD | $30.24 | Source Spec Material / Tool |
| Tie wire rolls | 98 ties | 10% | 1 rolls | USD | $8.00 | Source Spec Material / Tool |
Source links open a product search on the Amazon storefront for the selected currency. SiteSpecCalc may earn a commission. The link does not change the quantities above.
Ready-mix truck
$1,021.78
0.62 nominal 10 yd³ loads · 1 to order
80 lb bags
$1,883.25
60 lb alternative $2,008.80 · delivery weight 25,080 lb
| Thickness | Order yd³ | Order m³ | 80 lb bags | Rebar ft | Ready-mix | 80 lb cost |
|---|---|---|---|---|---|---|
| 4 in | 4.24 | 3.239 | 191 | 440 | $699.11 | $1,289.25 |
| 5 in | 4.73 | 3.613 | 213 | 440 | $779.78 | $1,437.75 |
| 6 in | 5.21 | 3.987 | 235 | 440 | $860.44 | $1,586.25 |
Show the deterministic formula
Slab ft³ = L × W × thickness ÷ 12. Thickened-edge extra = footing band × (footing depth − slab thickness), with corner squares counted once.
yd³ = ft³ ÷ 27. m³ = ft³ × 0.0283168. Weight uses 150 lb/ft³, then the header converts that pound total at 1 lb = 0.45359237 kg. 80 lb bags yield 0.6 ft³ and 60 lb bags yield 0.45 ft³. Currency changes the price labels only.
Bars across a span = floor(span ÷ spacing) + 1. Order sticks = that count, plus 10, 5, or 15 percent waste, cut from 20 ft and 6 m stock. Chairs = one per grid intersection.
Contractor sign-off
Project: 10 by 20 ft slab at 8 inches
Prepared by
Date
Verified by (PE / electrician / inspector)
License number
Signature
This sheet is an estimate for ordering and layout discussion. It is not a sealed design. Confirm the quantities with a licensed local professional and the authority having jurisdiction before you buy or build.
Engineering notes
This calculator assists in determining the specifications for a residential concrete slab measuring 10 ft by 20 ft with a thickness of 8 inches. The design incorporates #4 rebar bars spaced at 18 inches apart, following the guidelines set forth in the IRC R506.
Please note that soil design considerations are excluded from this calculation. It is crucial to ensure that the underlying soil is adequately assessed to support the slab's load-bearing requirements.
Code reference
IRC R506
Field questions
- What is the purpose of using #4 bars in the slab?
- The #4 bars provide reinforcement to the concrete slab, helping to prevent cracking and improve structural integrity.
- Why is soil design excluded from this calculation?
- Soil design is excluded because it requires specific geotechnical analysis that varies by location and is essential for ensuring the slab's stability.
- What does IRC R506 cover?
- IRC R506 provides guidelines for the design and construction of concrete slabs, including reinforcement and thickness requirements.
Explore Related Engineering Calculations
- 14 by 12 ft slab at 8 inches
- 14 by 14 ft slab at 4 inches
- 8 by 8 ft slab at 8 inches
- 8 by 10 ft slab at 4 inches
- 14 by 14 ft slab at 5 inches
- 14 by 14 ft slab at 6 inches
- 50 Amp EV Charger Wire Size at 50, 75, and 100 Feet
- Deck Stair Stringer Calculator, 36 to 96 Inch Rise
- 6/12 Roof Pitch, Rafter Length, and Shingle Bundles
- 20 ft dry, US 48×40 pallets: Pallet Count, CBM, and Payload