Skip to content
SiteSpecCalc

Length imperial. Weight lb. Currency USD. Weight uses 1 lb = 0.45359237 kg. Currency converts US-dollar planning prices and does not change volumes, counts, or geometry.

18 by 20 ft slab at 8 inches

Calculate the specifications for an 18 ft by 20 ft residential slab at 8 in thickness with #4 bars at 18 in spacing. Ensure compliance with IRC R506 standards.

Formula SSC-2026.1

Formula SSC-2026.1 · 4,000 PSI

Order volume

10.76 yd³

8.223 m³ placed+waste

Order weight

43,560 lb

19,758 kg

80 lb bags

484

12 pallets at 42 bags

60 lb bags

646

0.45 ft³ yield each

Rebar

664.00 ft

35 × 20 ft · 48 × 6 m · 488 lb

Ready-mix vs bags

$1,774.67

Truck $1,774.67 · 80 lb bags $3,267.00

Slab footprint and rebar gridLive scaled blueprint
18.00 ft20.00 ft#4 / 12 mm at 18 in OC · 8 in slab

Grid lines are equalized so the drawing stays readable. The order count uses on-center spacing with a bar at each end of the layout, then holds concrete cover in the field.

Bill of materials and shopping list
ItemNetWasteOrderUnit priceLine totalSource Spec Material / Tool
Ready-mix concrete9.78 yd³10%10.76 yd³ / 8.223 m³USD$1,774.67Source Spec Material / Tool
Short-load feeFull load—2 truck @ 10 yd³USD$0.00Source Spec Material / Tool
80 lb pre-mix bags440.0 bags10%484 bagsUSD$3,267.00Source Spec Material / Tool
60 lb pre-mix bags586.7 bags10%646 bagsUSD$3,488.40Source Spec Material / Tool
#4 rebar sticks, 20 ft35 sticks10%39 sticks / 48 × 6 mUSD$546.00Source Spec Material / Tool
Rebar chairs182 crossings10%201 chairsUSD$56.28Source Spec Material / Tool
Tie wire rolls182 ties10%1 rollsUSD$8.00Source Spec Material / Tool

Source links open a product search on the Amazon storefront for the selected currency. SiteSpecCalc may earn a commission. The link does not change the quantities above.

Ready-mix truck

$1,774.67

1.08 nominal 10 yd³ loads · 2 to order

80 lb bags

$3,267.00

60 lb alternative $3,488.40 · delivery weight 43,560 lb

Side-by-side thickness comparison at the same footprint
ThicknessOrder yd³Order m³80 lb bagsRebar ftReady-mix80 lb cost
4 in6.845.233308730$1,129.33$2,079.00
5 in7.825.981352730$1,290.67$2,376.00
6 in8.806.728396730$1,452.00$2,673.00
Show the deterministic formula

Slab ft³ = L × W × thickness ÷ 12. Thickened-edge extra = footing band × (footing depth − slab thickness), with corner squares counted once.

yd³ = ft³ ÷ 27. m³ = ft³ × 0.0283168. Weight uses 150 lb/ft³, then the header converts that pound total at 1 lb = 0.45359237 kg. 80 lb bags yield 0.6 ft³ and 60 lb bags yield 0.45 ft³. Currency changes the price labels only.

Bars across a span = floor(span ÷ spacing) + 1. Order sticks = that count, plus 10, 5, or 15 percent waste, cut from 20 ft and 6 m stock. Chairs = one per grid intersection.

Engineering notes

This calculator is designed to assist in determining the specifications for a residential slab measuring 18 ft by 20 ft with a thickness of 8 inches. The reinforcement consists of #4 bars spaced 18 inches apart. Please note that soil design considerations are excluded from this calculation.

Ensure that your design adheres to the requirements outlined in IRC R506 for concrete slabs, which includes guidelines for thickness, reinforcement, and other structural considerations.

Code reference

IRC R506 - Concrete Floors on Ground

Field questions

What is the purpose of using #4 bars in the slab?
The #4 bars provide tensile strength to the concrete slab, helping to prevent cracking and ensuring structural integrity.
Why is soil design excluded from this calculation?
Soil design is a separate consideration that depends on the specific site conditions and soil characteristics, which are not covered in this calculator.
What thickness is recommended for residential slabs?
For residential slabs, a thickness of 4 to 6 inches is commonly recommended, but in this case, an 8-inch thickness is specified for added strength.
How do I ensure compliance with IRC R506?
To ensure compliance with IRC R506, follow the guidelines for slab thickness, reinforcement placement, and other structural requirements as outlined in the code.

Explore Related Engineering Calculations