28×40 Slab at 6 Inches: Rebar, Bags, and Truck
A 28 by 40 ft pad at 6 in, with the thickness table repeating the takeoff at the other standard depths.
Formula SSC-2026.1
Formula SSC-2026.1 · 4,000 PSI
Order volume
22.81 yd³
17.443 m³ placed+waste
Order weight
92,400 lb
41,912 kg
80 lb bags
1,027
25 pallets at 42 bags
60 lb bags
1,369
0.45 ft³ yield each
Rebar
1,516.00 ft
92 × 20 ft · 111 × 6 m · 1,114 lb
Ready-mix vs bags
$3,764.44
Truck $3,764.44 · 80 lb bags $6,932.25
Grid lines are equalized so the drawing stays readable. The order count uses on-center spacing with a bar at each end of the layout, then holds concrete cover in the field.
| Item | Net | Waste | Order | Unit price | Line total |
|---|---|---|---|---|---|
| Ready-mix concrete | 20.74 yd³ | 10% | 22.81 yd³ / 17.443 m³ | USD | $3,764.44 |
| Short-load fee | Full load | — | 3 truck @ 10 yd³ | USD | $0.00 |
| 80 lb pre-mix bags | 933.3 bags | 10% | 1,027 bags | USD | $6,932.25 |
| 60 lb pre-mix bags | 1,244.4 bags | 10% | 1,369 bags | USD | $7,392.60 |
| #4 rebar sticks, 20 ft | 92 sticks | 10% | 102 sticks / 111 × 6 m | USD | $1,428.00 |
| Rebar chairs | 513 crossings | 10% | 565 chairs | USD | $158.20 |
| Tie wire rolls | 513 ties | 10% | 2 rolls | USD | $16.00 |
Ready-mix truck
$3,764.44
2.28 nominal 10 yd³ loads · 3 to order
80 lb bags
$6,932.25
60 lb alternative $7,392.60 · delivery weight 92,400 lb
| Thickness | Order yd³ | Order m³ | 80 lb bags | Rebar ft | Ready-mix | 80 lb cost |
|---|---|---|---|---|---|---|
| 4 in | 15.21 | 11.629 | 685 | 1,668 | $2,509.63 | $4,623.75 |
| 5 in | 19.01 | 14.536 | 856 | 1,668 | $3,137.04 | $5,778.00 |
| 6 in | 22.81 | 17.443 | 1,027 | 1,668 | $3,764.44 | $6,932.25 |
Show the deterministic formula
Slab ft³ = L × W × thickness ÷ 12. Thickened-edge extra = footing band × (footing depth − slab thickness), with corner squares counted once.
yd³ = ft³ ÷ 27. m³ = ft³ × 0.0283168. Weight uses 150 lb/ft³, then the header converts that pound total at 1 lb = 0.45359237 kg. 80 lb bags yield 0.6 ft³ and 60 lb bags yield 0.45 ft³. Currency changes the price labels only.
Bars across a span = floor(span ÷ spacing) + 1. Order sticks = that count, plus 10, 5, or 15 percent waste, cut from 20 ft and 6 m stock. Chairs = one per grid intersection.
Contractor sign-off
Project: 28×40 Slab at 6 Inches: Rebar, Bags, and Truck
Prepared by
Date
Verified by (PE / electrician / inspector)
License number
Signature
This sheet is an estimate for ordering and layout discussion. It is not a sealed design. Confirm the quantities with a licensed local professional and the authority having jurisdiction before you buy or build.
Engineering notes
A 28 by 40 ft rectangle at 6 in is about 20.74 cubic yards before waste. This page adds 10 percent waste, prices 4,000 PSI ready-mix against 80 lb and 60 lb bags, and lays #4 bar at 18 in on center. The comparison table repeats the same footprint at 4, 5, and 6 in so the extra inch of thickness is only extra volume, not a different grid. Soil bearing, vapor retarder, and joints are not designed here.
Code reference
IRC R506.1 sets a 3.5 in minimum for concrete slab-on-ground floors. Reinforcement cover and spacing follow ACI 318 practice and the local inspector. This quantity takeoff is not a soils or structural design.
Field questions
- How many cubic yards is a 28 by 40 slab at 6 in before waste?
- Length times width times thickness in feet, divided by 27, is about 20.74 cubic yards. The order line then applies the waste factor on the page.
- Does the rebar count change when the slab gets thicker?
- No. The grid follows the length, width, and spacing. Thickness changes volume, weight, bags, and the ready-mix price.
- When is a truck cheaper than bags?
- Compare the ready-mix line, including any short-load fee under 4 yards, with the 80 lb bag line. Both use the prices typed on the page.
Explore Related Engineering Calculations
- 20×20 Garage Slab: 4 Inch vs 6 Inch
- 10×12 Shed Pad: Bags vs Ready-Mix
- 24×30 Monolithic Shop Slab with Rebar
- 6×6 Hot Tub Pad, 6 Inch Reinforced
- 12×40 Concrete Driveway Thickness and Cost
- 30×40 Barn Slab at 6 Inches and 4,000 PSI
- 50 Amp EV Charger Wire Size at 50, 75, and 100 Feet
- Deck Stair Stringer Calculator, 36 to 96 Inch Rise
- 6/12 Roof Pitch, Rafter Length, and Shingle Bundles
- 20 ft dry, US 48×40 pallets: Pallet Count, CBM, and Payload