Skip to content
SiteSpecCalc

Length imperial. Weight lb. Currency USD. Weight uses 1 lb = 0.45359237 kg. Currency converts US-dollar planning prices and does not change volumes, counts, or geometry.

20×20 Garage Slab: 4 Inch vs 6 Inch

A 20 ft square garage pad at 4 in, with the comparison table repeating the takeoff at 6 in.

Formula SSC-2026.1

Formula SSC-2026.1 · 4,000 PSI

Order volume

5.43 yd³

4.153 m³ placed+waste

Order weight

22,000 lb

9,979 kg

80 lb bags

245

6 pallets at 42 bags

60 lb bags

326

0.45 ft³ yield each

Rebar

560.00 ft

28 × 20 ft · 56 × 6 m · 411 lb

Ready-mix vs bags

$896.30

Truck $896.30 · 80 lb bags $1,653.75

Slab footprint and rebar gridLive scaled blueprint
20.00 ft20.00 ft#4 / 12 mm at 18 in OC · 4 in slab

Grid lines are equalized so the drawing stays readable. The order count uses on-center spacing with a bar at each end of the layout, then holds concrete cover in the field.

Bill of materials and shopping list
ItemNetWasteOrderUnit priceLine total
Ready-mix concrete4.94 yd³10%5.43 yd³ / 4.153 m³USD$896.30
Short-load feeFull load—1 truck @ 10 yd³USD$0.00
80 lb pre-mix bags222.2 bags10%245 bagsUSD$1,653.75
60 lb pre-mix bags296.3 bags10%326 bagsUSD$1,760.40
#4 rebar sticks, 20 ft28 sticks10%31 sticks / 56 × 6 mUSD$434.00
Rebar chairs196 crossings10%216 chairsUSD$60.48
Tie wire rolls196 ties10%1 rollsUSD$8.00

Ready-mix truck

$896.30

0.54 nominal 10 yd³ loads · 1 to order

80 lb bags

$1,653.75

60 lb alternative $1,760.40 · delivery weight 22,000 lb

Side-by-side thickness comparison at the same footprint
ThicknessOrder yd³Order m³80 lb bagsRebar ftReady-mix80 lb cost
4 in5.434.153245616$896.30$1,653.75
6 in8.156.230367616$1,344.44$2,477.25
Show the deterministic formula

Slab ft³ = L × W × thickness ÷ 12. Thickened-edge extra = footing band × (footing depth − slab thickness), with corner squares counted once.

yd³ = ft³ ÷ 27. m³ = ft³ × 0.0283168. Weight uses 150 lb/ft³, then the header converts that pound total at 1 lb = 0.45359237 kg. 80 lb bags yield 0.6 ft³ and 60 lb bags yield 0.45 ft³. Currency changes the price labels only.

Bars across a span = floor(span ÷ spacing) + 1. Order sticks = that count, plus 10, 5, or 15 percent waste, cut from 20 ft and 6 m stock. Chairs = one per grid intersection.

Engineering notes

A 20 by 20 ft garage at 4 in is 4.94 cubic yards before waste. At 10 percent waste the order is about 5.43 yards, which is often a short load. The same footprint at 6 in is 50 percent more concrete. Use the thickness table on this page before you choose 4 in for a passenger car or 6 in for a heavier vehicle. The default grid is #4 bar at 18 in on center. Hold about 3 in of cover where concrete is cast against earth, and confirm the base compaction separately.

Code reference

IRC R506.1 sets a 3.5 in minimum for concrete slab-on-ground floors. Reinforcement cover and spacing follow ACI 318 practice and the local inspector. This quantity takeoff is not a soils or structural design.

Field questions

Is 4 inches enough for a two-car garage?
Many passenger-car garages are built at 4 in over a compacted base, but a heavier truck or poor soil often pushes the spec to 5 or 6 in. The table shows both quantities.
How many yards is a 20x20 by 4 inch slab?
The placed volume is 133.33 cubic feet, or 4.94 cubic yards, before the waste factor. At 10 percent the order is about 5.43 cubic yards.
Does the 6 inch option change the rebar count?
Thickness does not change the grid count. It changes volume, weight, bags, and the ready-mix price. The highlighted row is the thickness currently selected.