8×10 Generator Pad, 8 Inch, 5,000 PSI

A heavy 8 in equipment pad for a generator, with a #5 mat.

Formula SSC-2026.1

Formula SSC-2026.1 · 5,000 PSI

Order volume

2.07 yd³

1.586 m³ placed+waste

Order weight

8,400 lb

3,810 kg

80 lb bags

94

3 pallets at 42 bags

60 lb bags

125

0.45 ft³ yield each

Rebar

178.00 ft

20 × 20 ft · 20 × 6 m · 195 lb

Ready-mix vs bags

$467.22

Truck $467.22 · 80 lb bags $634.50

Slab footprint and rebar gridLive scaled blueprint
10.00 ft8.00 ft#5 / 16 mm at 12 in OC · 8 in slab

Grid lines are equalized so the drawing stays readable. The order count uses on-center spacing with a bar at each end of the layout, then holds concrete cover in the field.

Bill of materials and shopping list
ItemNetWasteOrderUnit priceLine total
Ready-mix concrete1.98 yd³5%2.07 yd³ / 1.586 m³USD$342.22
Short-load feeUnder 4 yd³—1 truck @ 10 yd³USD$125.00
80 lb pre-mix bags88.9 bags5%94 bagsUSD$634.50
60 lb pre-mix bags118.5 bags5%125 bagsUSD$675.00
#5 rebar sticks, 20 ft20 sticks5%21 sticks / 20 × 6 mUSD$462.00
Rebar chairs99 crossings5%104 chairsUSD$29.12
Tie wire rolls99 ties5%1 rollsUSD$8.00

Ready-mix truck

$467.22

0.21 nominal 10 yd³ loads · 1 to order

80 lb bags

$634.50

60 lb alternative $675.00 · delivery weight 8,400 lb

Side-by-side thickness comparison at the same footprint
ThicknessOrder yd³Order m³80 lb bagsRebar ftReady-mix80 lb cost
6 in1.561.18970187$381.67$472.50
8 in2.071.58694187$467.22$634.50
Show the deterministic formula

Slab ft³ = L × W × thickness ÷ 12. Thickened-edge extra = footing band × (footing depth − slab thickness), with corner squares counted once.

yd³ = ft³ ÷ 27. m³ = ft³ × 0.0283168. Weight uses 150 lb/ft³, then the header converts that pound total at 1 lb = 0.45359237 kg. 80 lb bags yield 0.6 ft³ and 60 lb bags yield 0.45 ft³. Currency changes the price labels only.

Bars across a span = floor(span ÷ spacing) + 1. Order sticks = that count, plus 10, 5, or 15 percent waste, cut from 20 ft and 6 m stock. Chairs = one per grid intersection.

Engineering notes

Eight by ten feet at 8 in is 1.98 cubic yards before waste. The mat is #5 at 12 in because the pad is thick and the load is concentrated. Five percent waste is the default. 5,000 PSI does not change the cubic yards. Type the plant price for that mix into the ready-mix field. Vibration isolation and the generator anchor pattern come from the equipment drawing.

Code reference

IRC R506.1 sets a 3.5 in minimum for concrete slab-on-ground floors. Reinforcement cover and spacing follow ACI 318 practice and the local inspector. This quantity takeoff is not a soils or structural design.

Field questions

Why #5 bars on a small pad?
The preset matches a heavy equipment pad, not a sidewalk. #5 at 12 in raises linear feet and stick weight. Change the size if the equipment pad detail shows #4.
Is 8 inches the same as two 4 inch lifts?
The volume is one 8 in thickness. Placement in lifts is a means-and-methods choice and does not change the cubic yards.
How heavy is the concrete itself?
Order weight uses 150 lb per cubic foot times the waste-adjusted volume. The generator weight is extra.