10×10 Slab at 4 Inches: Rebar, Bags, and Truck
A 10 by 10 ft pad at 4 in, with the thickness table repeating the takeoff at the other standard depths.
Formula SSC-2026.1
Formula SSC-2026.1 · 4,000 PSI
Order volume
1.36 yd³
1.038 m³ placed+waste
Order weight
5,500 lb
2,495 kg
80 lb bags
62
2 pallets at 42 bags
60 lb bags
82
0.45 ft³ yield each
Rebar
140.00 ft
14 × 20 ft · 14 × 6 m · 103 lb
Ready-mix vs bags
$349.07
Truck $349.07 · 80 lb bags $418.50
Grid lines are equalized so the drawing stays readable. The order count uses on-center spacing with a bar at each end of the layout, then holds concrete cover in the field.
| Item | Net | Waste | Order | Unit price | Line total |
|---|---|---|---|---|---|
| Ready-mix concrete | 1.23 yd³ | 10% | 1.36 yd³ / 1.038 m³ | USD | $224.07 |
| Short-load fee | Under 4 yd³ | — | 1 truck @ 10 yd³ | USD | $125.00 |
| 80 lb pre-mix bags | 55.6 bags | 10% | 62 bags | USD | $418.50 |
| 60 lb pre-mix bags | 74.1 bags | 10% | 82 bags | USD | $442.80 |
| #4 rebar sticks, 20 ft | 14 sticks | 10% | 16 sticks / 14 × 6 m | USD | $224.00 |
| Rebar chairs | 49 crossings | 10% | 54 chairs | USD | $15.12 |
| Tie wire rolls | 49 ties | 10% | 1 rolls | USD | $8.00 |
Ready-mix truck
$349.07
0.14 nominal 10 yd³ loads · 1 to order
80 lb bags
$418.50
60 lb alternative $442.80 · delivery weight 5,500 lb
| Thickness | Order yd³ | Order m³ | 80 lb bags | Rebar ft | Ready-mix | 80 lb cost |
|---|---|---|---|---|---|---|
| 4 in | 1.36 | 1.038 | 62 | 154 | $349.07 | $418.50 |
| 5 in | 1.70 | 1.298 | 77 | 154 | $405.09 | $519.75 |
| 6 in | 2.04 | 1.557 | 92 | 154 | $461.11 | $621.00 |
Show the deterministic formula
Slab ft³ = L × W × thickness ÷ 12. Thickened-edge extra = footing band × (footing depth − slab thickness), with corner squares counted once.
yd³ = ft³ ÷ 27. m³ = ft³ × 0.0283168. Weight uses 150 lb/ft³, then the header converts that pound total at 1 lb = 0.45359237 kg. 80 lb bags yield 0.6 ft³ and 60 lb bags yield 0.45 ft³. Currency changes the price labels only.
Bars across a span = floor(span ÷ spacing) + 1. Order sticks = that count, plus 10, 5, or 15 percent waste, cut from 20 ft and 6 m stock. Chairs = one per grid intersection.
Contractor sign-off
Project: 10×10 Slab at 4 Inches: Rebar, Bags, and Truck
Prepared by
Date
Verified by (PE / electrician / inspector)
License number
Signature
This sheet is an estimate for ordering and layout discussion. It is not a sealed design. Confirm the quantities with a licensed local professional and the authority having jurisdiction before you buy or build.
Engineering notes
A 10 by 10 ft rectangle at 4 in is about 1.23 cubic yards before waste. This page adds 10 percent waste, prices 4,000 PSI ready-mix against 80 lb and 60 lb bags, and lays #4 bar at 18 in on center. The comparison table repeats the same footprint at 4, 5, and 6 in so the extra inch of thickness is only extra volume, not a different grid. Soil bearing, vapor retarder, and joints are not designed here.
Code reference
IRC R506.1 sets a 3.5 in minimum for concrete slab-on-ground floors. Reinforcement cover and spacing follow ACI 318 practice and the local inspector. This quantity takeoff is not a soils or structural design.
Field questions
- How many cubic yards is a 10 by 10 slab at 4 in before waste?
- Length times width times thickness in feet, divided by 27, is about 1.23 cubic yards. The order line then applies the waste factor on the page.
- Does the rebar count change when the slab gets thicker?
- No. The grid follows the length, width, and spacing. Thickness changes volume, weight, bags, and the ready-mix price.
- When is a truck cheaper than bags?
- Compare the ready-mix line, including any short-load fee under 4 yards, with the 80 lb bag line. Both use the prices typed on the page.
Explore Related Engineering Calculations
- 20×20 Garage Slab: 4 Inch vs 6 Inch
- 10×12 Shed Pad: Bags vs Ready-Mix
- 24×30 Monolithic Shop Slab with Rebar
- 6×6 Hot Tub Pad, 6 Inch Reinforced
- 12×40 Concrete Driveway Thickness and Cost
- 30×40 Barn Slab at 6 Inches and 4,000 PSI
- 50 Amp EV Charger Wire Size at 50, 75, and 100 Feet
- Deck Stair Stringer Calculator, 36 to 96 Inch Rise
- 6/12 Roof Pitch, Rafter Length, and Shingle Bundles
- 20 ft dry, US 48×40 pallets: Pallet Count, CBM, and Payload